... 

Large Loss Lessons Learned
Corrosive Chemical Vapor Release

During Valve Replacement
Two employees were replacing piping, gauges and valves on a tank containing a highly irritating and corrosive gas at a customer’s site. The day before the accident the employees tested the safety shower to verify there was water flow, and then began evacuating the tank while maintaining the system under negative pressure. The downstream valves connected to the plant process were not locked or tagged out. When the two employees arrived on the second day they began removing valves without checking the system to verify if it was still under negative pressure, without checking the position of the downstream valves, and without testing the safety shower again for water flow. While unbolting a flange at the base of the tank pressurized gas vaporized into the employees face and upper body. He irrigated his face with a squirt bottle, doused himself with a 5 gallon water jug, ran to the safety shower 40 feet away and tried to operate the shower, but it did not provide any water flow. The employee was wearing chemical gloves, goggles, a face shield, hat and cotton clothing. He was subsequently transferred to the nurses’ station and put into a shower prior to taking an ambulance and helicopter evacuation to a local hospital.

Consequences

  • Second-degree chemical burns to his face, upper left arm and upper left torso
  • Three weeks in a burn unit at the hospital
  • Months of lost time and therapy to recover from the injury
  • Total Incurred Costs of $841,000

Lessons Learned

  • Require that employees hand record all gauge readings on a job task form prior to and following any work; this will prompt employees to mentally check that the lines are under the desired pressure.
  • As part of all customer agreements, the responsibility for identifying all required process safety locks should be defined. Both the customer and subcontractor should identify and review all process isolation and safety locks and/or tags that are applied.
  • A reassessment of all of the personal protective equipment should be performed, to determine if alternative PPE should be incorporated when working on projects that involve process lines that are or have been previously charged.
  • All safety support equipment on the site should be identified and tested daily prior to commencing work to verify that all systems are operable and accessible.

Please contact the Risk Control division of XL Insurance at 800- 327-1414 if you have any questions regarding PPE Hazard Assessments, job hazard analyses, lockout/tagout programs, or other health, safety, or environmental issues affecting your operations.

"XL Insurance" is a registered trademark of XL Capital Ltd. XL Insurance is the global brand used by member insurers of the XL Capital Ltd group of companies.


For general information purposes only. Contents should not be construed or used as legal advice or opinion.

XL Insurance
520 Eagleview Blvd
PO Box 636
Exton, PA 19341-0636
Tel: +1 800-327-1414
Fax: +1 610-458-8667
www.xlinsurance.com/environmental

© X.L. America, Inc. All rights reserved.

FUNDAMENTAL STRENGTH – CAPITAL AND PEOPLE

 
Back