|
Mobile Cranes: The Importance
Of Lift Assessments
Mobile crane work involves lifting and
placing many types of materials in both “safe”
and hazardous locations. Although large or complicated
lifts are easily recognized as being of a critical nature
requiring additional planning, the hazards associated
with smaller lifts may be less obvious. Therefore, it
is important to conduct a lift assessment regardless
of the specifics of the lift. Equally as important is
a firm understanding of the operator and supervisor’s
responsibilities during any type of lift.
Lift Assessment Process
Currently, there is no consensus standard
regarding when formal lift plans are required. One widely
recognized standard, from the Construction Safety Association
of Ontario, defines a critical lift as those where the
gross load is within 75 percent of the rated capacity
of the crane. Another standard is the Exxon Crane guide,
which defines a critical lift as greater than 90 percent
of the rated capacity. The bottom line is that each
company should establish its own critical lift guidelines.
The degree to which the guidelines are applied depends
on the results of the Lift Assessment Process. Lifts
can be classified by the degree of difficulty. An example
of a Lift Assessment Process, as developed and recommended
by Exxon, is discussed below. A Lift Classification
Flow Chart describes the process.
- A lift planner should use the Lift Classification
Flow Chart in determining the classification of the
lift and the planning required.
- All critical lifts should have a formal Critical
Lift Plan. Outside engineering help may be required
to fully assess and resolve all important load and
site factors.
- More routine lifts are classified as Non-Standard.
The Lift Planning Process is less involved than for
a Critical Lift and is documented on a Lift Evaluation
Form.
Daily Crane Operation Log
Most lifts will be classified as Standard
and require less planning and documentation. This type
of planning can be documented in a Daily Crane Operation
Log. A Daily Crane Operation Log is designed to record
basic lift information and confirms the load is within
the rated capacity of the crane. One of the main reasons
for completing a log is that it requires the crane operator
to document even the most fundamental aspects of a lift,
thereby decreasing the chances of lifts being made in
an unsafe manner.
Lift Evaluation Form
A Lift Evaluation Form (LEF) should be
used when a lift is determined to be Non-Standard. The
LEF is a one-page document. To complete the LEF, the
supervisor must evaluate the basic questions noted in
the flow chart below, and with the aid of the operator,
determine if the gross load is (1) less than 20 tons,
and (2) between 80 percent and 90 percent of the manufacturer’s
load chart during all parts of the lift. This information,
in addition to some basic site evaluation remarks, is
recorded on the LEF.
Sign-offs should include the operator,
lift supervisor, area supervisor and engineer.
Critical Lift Plan
A Critical Lift Plan (CLP) consists of
drawings, specifications and procedures necessary to
accurately assess all important load and site factors
relating to a critical lift. However, most lifts do
not involve all of the factors listed in the flow chart
above, in which case a minimum level of information
is required to comprise an adequate lift plan. Main
components of the CLP include:
- Elevation View Drawing
- Plan View Drawing
- Lift Analysis
All potential complicating issues for
any lift should be addressed in the lift plan. Some
of the precautions that should be addressed by the CLP
are:
- Supporting Surface – Ground compact and stable?
- Blocking – Outrigger blocking used and crawlers
on pads or cribbing (unless the crane sits on a concrete
pad)?
- Level – Machinery deck or boom foot pins
absolutely level?
- Load – Load weight determined exactly?
- Center of Gravity – Location of the load’s
center of gravity determined and the crane hook positioned
above it?
- Load Radius – Measured exactly?
- Boom Length – Determined exactly?
- Boom Angle – Boom angle, if necessary for
determining the crane’s capacity, determined
exactly? (Do not rely on the crane’s boom angle
indicator.)
- Wind – Wind effects considered? (If wind
speeds are greater 30 mph, do not make the lift. If
greater than 20 mph, consider postponing.)
o Overhead Exposures – Measure clearance exactly.
- Reeving – Balanced?
- Load Rigging – Checked for adequacy and security?
Exact weight of rigging known?
- Operation – Reinforced the need to make all
controls, machine and load movements as slowly and
smoothly as possible?
- Unstable Load – Large, thin or potentially
unstable pieces to be lifted?
- Multi-crane Lifts – Will the load require
more than one crane to perform the lift?
- Congested Areas – Will the lift be performed
in areas where structures, pipe racks, power lines
or other obstacles are present?
- Turning – Will the lift involve turning or
flipping a piece from one side to the other?
- Power Line Exposure – Lines de-energized;
mandatory distance from arching?
The site supervisor is responsible for
ensuring the CLP is developed and reviewed before the
lift is made. The Plan should be presented to the facility
owner as appropriate. Responsibilities for the lift
are divided among several individuals including the
operator and the site supervisor.
Note: In the event that
it becomes necessary to deviate from the CLP, the lift
should be re-evaluated and the CLP should be revised.
Conclusion
The lift plan process should be followed
regardless of the specifics of the lift. The general
guidelines outlined above are important factors for
any company to consider when developing and implementing
a Lift Assessment Process.
XL Environmental • Risk Control Division •
520 Eagleview Boulevard, PO Box 636, Exton, PA 19341
• Phone: 800-327-1414 • Fax: 610-458-7285
• xlenvironmental.com
XL Environmental is a division of XL Specialty Insurance
Company.
|