|
Contractors: Environmental Risk
Management Recommendations for Contractors
Almost every construction project involves
environmental risks. Environmental impairment comes
in many forms and results in fines, delays, unwanted
liabilities, cost overruns, change orders and possible
work stoppages. Following are ten common environmental
recommendations for all types of construction contractors,
as well as case histories and alternative actions that
may have reduced the impact of, or prevented, these
situations.
1) Beware Of Mold
Recommendation: Consider adopting
a mold awareness program that includes employee training
on techniques to prevent mold growth, and management
procedures for containment and remediation decisions
if mold is discovered at a project site. The program
should include a schedule for routine inspections for
water infiltration, schedule-sequencing considerations
for trades and materials, ventilation of enclosed spaces,
and methodology for repairing water infiltration. The
program should also include communication methods to
project managers and owners including, but not limited
to, contract provisions for dealing with discovered
mold, response timing and methodology, and responsibilities
associated with remediation of mold growth.
Case History: A general contractor
demanded that a drywall subcontractor install fire-retardant
wallboard in an elevator pit and a pipe chase before
the roof of a building was complete. The subcontractor
objected, claiming that the wallboard could become saturated
in the event of rain. During a weekend storm, the wallboard
became saturated and mold began to grow. The general
contractor demanded removal and replacement of the moldy
wallboard at no cost; the subcontractor refused, citing
his documented previous objections. The general contractor
eventually hired another firm to remove and replace
the affected wallboard. By that time, the mold had spread
over a large area.
Alternative Action: The general contractor
should consider the following actions for the future:
- Sequence construction activities so that moisture
sensitive materials are delivered to the site and
installed once the building envelope is complete and
dry storage is available.
- Initiate a corporate mold program so that project
participants are aware of the potential liabilities.
- Include potential mold remediation with subcontractors
in the plans, specifications, and contract so that
responsibilities are clearly delineated before work
is begun.
- Listen to the concerns of the subcontractors; the
project could have been completed in a more timely,
professional and efficient fashion if the drywall
subcontractor’s opinion had been respected.
2) Obtain Environmental Information
Recommendation: Firms associated with
construction or demolition at a project site should
obtain information on the site’s environmental
history from the owner or firm responsible for the project
during the bidding phase or prior to signing a contract.
Case History: An excavation contractor
unknowingly spread petroleum-contaminated soil across
a project site during fill operations for a housing
project. The contractor was brought into a lawsuit for
exacerbating the extent of the site’s contamination.
After lengthy deliberations, the contractor was eventually
dismissed from the lawsuit, after spending more than
$250,000 on defense.
Alternative Action: All contractors
involved with a project are entitled to request environmental
information about the site from the site’s owner.
Prior to signing a contract, obtain this information
which is available from several sources:
- Phase I Environmental Site Assessment (ESA)
- Phase II Environmental Site Assessment
- Pre-bid site walk through
Phase I ESAs typically are required by a lender before
the owner receives financing for the project. A Phase
I includes a search of property titles, regulatory databases,
and other public information to determine past property
uses, which may give insight into the potential for
environmental contamination. Phase I ESAs may include
visual observations from a property tour.
Phase II ESAs are performed if there is probability
of past contamination. A Phase II defines the extent
and concentration of site contamination through the
analysis of groundwater, soil, and existing building
material samples.
Examples of environmental contamination that a contractor
should look for during a pre-bid site tour include:
- Stained soil and stressed vegetation -- may indicate
soil contamination
- Asbestos-containing material
- Lead paint or roofing materials
- Mercury-containing fluorescent light fixtures
- PCB oils in old transformers
- Fill and vent pipes -- may indicate underground
storage tanks
- Hazardous atmospheres and product piping in manholes
- Bird droppings -- the associated dust can cause
irritation and illness
3) Ensure Fill Material Is Clean
Recommendation: Analyze fill materials
brought to a project site or request a certification
of testing from the source of the fill. This is especially
important if the soil is being offered at a “reduced”
price or if it is coming from a suspect source. Keep
in mind that not all contamination is detectable by
sight or smell.
Case History: A contractor performed
clearing and grubbing on an apparently undeveloped piece
of property. Though the contamination was not visibly
detectable and there was no odor, the site was previously
used as a dumpsite for dredge spoils from a local harbor.
The soils were highly contaminated with cadmium, lead,
and other heavy metals. The project was delayed and
the cleanup costs were triple the contractor’s
expected profit.
Alternative Action: The contractor
could take several separate courses of action before
disturbing the soil at a project site:
- Obtain Phase I and II ESA information
- Request a certificate from the landowner stating
the soil is free of hazardous materials.
- Have an environmental consulting analyze the soil
for chemical contaminants.
4) Use Clear Contractual Language
Recommendation: Contractors and project
owners are encouraged to include contractual clauses
for the handling of known contamination and the discovery
of unanticipated hazardous materials at a project site.
Clear guidelines for the ownership, remediation, hiring
of specialty subcontractors, and disposal of site waste
should be clearly defined.
Case History: During site grading
operations, a contractor discovered five buried tanks
that contained unknown materials. The contract stated
the contractor was responsible for all known and unknown
underground conditions. The contractor subcontracted
the removal of the tanks and surrounding contaminated
soil. Change orders submitted to the owner for the costs
of remediation and the associated delay were denied,
based on the contract terms and conditions. The contractor’s
insurance carrier denied a claim for reimbursement based
on the absolute pollution exclusion in the general liability
policy.
Alternative Action: Clauses that deal
with environmental issues need to be carefully negotiated
into the contract and the roles and responsibilities
of each involved party made clear. Sample clauses are
available from trade associations; however, the inclusion
of these terms in any contract should be reviewed by
local legal counsel to reflect project-specific conditions.
Clauses should address:
- Known pre-existing contamination
- Discovery of unknown existing contamination
- Remediation responsibilities
- Schedule impacts
- Payment terms
- Indemnification
5) Don’t Sign Waste Manifests
Recommendation: Waste manifests are
used for tracking the handling, transportation, and
disposal of hazardous and other regulated wastes. The
individual signing these documents assumes responsibility
for the proper characterization, handling, and disposal
of the materials. In the event that wastes are incorrectly
managed, your firm may be held liable for future cleanup
costs and penalties. Unless you are the generator, the
transporter, or the final disposal firm, no one from
your firm should sign manifests for the disposal of
hazardous wastes.
Case History: A site development contractor
was held liable for the cleanup of illegally disposed
55-gallon drums found at a construction site and collected
by an unlicensed waste hauler. Instead of transporting
the drums to a permitted landfill, the hauler dumped
the drums in an out-of-state rural field. The contractor
was listed as a Potentially Responsible Party (PRP)
along with the client because the contractor’s
name was on the manifest.
Alternative Action: Environmental
engineering firms or contractors hired by an owner of
a site and charged with managing the waste disposal
are not the generator. Under every circumstance, the
generator of the waste scheduled for disposal is the
person or firm in control of the site and the firm that
is responsible for the cleanup. These entities should
sign the manifests. If the owner requests that the contractor
sign the manifest as an agent of the owner, the contractor
becomes ultimately responsible. Receipt and permanent
retention of the completed manifest from the disposal
facility by the owner is of prime importance as this
is the only record of proper disposal.
6) Train Workers In Spill Prevention
Recommendation: Aboveground storage tanks should be
in secondary containment large enough to contain 110%
of the tank’s volume. Employees responding to
a spill of a bulk liquid should be trained in the proper
use of the available spill response materials and personal
protective equipment. This training must be rehearsed
at least annually and documented.
Case History: A contractor had a 500-gallon
diesel fuel tank on a bridge deck while performing maintenance
and repaving activities. The tank was inadvertently
punctured by a forklift operator and the contents spilled
to the river below, contaminating the water and both
banks. The cleanup cost the contractor more than $10,000
and resulted in state-issued fines. There were no spill
containment supplies at the site and the response time
for a remediation contractor was several hours. By then,
the fuel had spread downstream.
Alternative Action: Proactive procedures
and equipment for aboveground storage tanks include:
- Use tanks that are equipped with secondary containment
pans and rain shields to add both limited collision
protection and primary containment in the event of
unwanted impact or structural failure
- Provide collision protection to avoid impact by
heavy equipment
- Place an earth berm around the tank if the tank
is not in a containment pan and line the berms and
bottom of the impoundment with poly-ethylene to prevent
spilled material from saturating the underlying soil.
- Provide adequate spill containment materials suitable
for use in water and on soil; store materials in a
pre-determined, dry and easily-accessible area on
the project site.
- Train selected site employees in emergency response
procedures in the event of a release.
- Keep the telephone number of a spill response firm
readily available and permit employees to contact
the firm without obtaining approval from the corporate
office.
7) Contact ‘One Call’ Services
Recommendation: Contractors responsible
for intrusive activities should contact the local “One
Call” service to locate buried utilities in the
vicinity of planned activities. These calls and planned
site visits are documented with a confirmation number
issued at the time of the initial call. Requirements
for the lead time of placing a call in advance of excavation
activities vary by state. Therefore, a thorough understanding
of local regulations is required.
Case History: A utility contractor
was installing new overhead electrical lines. Their
subcontractor was installing the new utility poles and
struck a buried sewer line with the auger. The utility
contractor was held liable for the actions of the subcontractor
through contractual liability and paid $90,000 for the
sewage cleanup and repairs of the sewer line.
Alternative Action: The subcontractor
should have contacted the local “One Call”
system that is available in all 50 states and the District
of Columbia. The utility contractor should have ensured
the “One Call” contact and accuracy of the
drilling location. This provision can be included in
the subcontract. If the utilities are marked and one
is struck outside of the exclusion zone, the contractor
may not be liable for the cleanup and repairs.
8) Install Erosion and Sediment Control
Recommendation: Erosion and sediment
controls should be installed on any construction site
in excess of one acre or where there is a potential
to contaminate a water body or storm water collection
system. These controls should be inspected after installation,
as well as prior to and after a significant rain event.
Examples of these controls include regular silt fence,
“super” silt fence, rip rap swales, hay
bales and sedimentation basins, and inlet filters.
Case History: A contractor developing
a site for a commercial entity had installed erosion
and sediment controls as per the project’s plans
and specifications; however, these controls were not
routinely inspected and maintained. After a very heavy
rainfall, the two local streams were contaminated with
sediment that was traced back to the site. State and
county environmental agencies levied fines for violations
in excess of several hundred thousand dollars. These
fines and penalties may not be covered by any available
insurance policies as they may be interpreted as unlawful
acts.
Alternative Action: Regular maintenance
and inspection of a site’s erosion controls are
important. Contractors should maintain a supply of these
controls at the site, or have them readily available,
in the event an inspection finds an area requiring repair.
Documentation of these inspections should be retained
in a project file. If a breach occurs, the documentation
may assist in a reduction of the fine amount and/or
the number of violations.
9) Consider Subcontracts and Pollution Insurance
Recommendation: Consistently use written
agreements that contain language in favor of your firm
with all subcontractors. Contracts should contain the
following clauses, at a minimum:
- Indemnification
- Hold harmless
- Inclusion of the general contract by reference
- Discovery and management of hazardous material
- Insurance requirements at least equal to those
in the general contract
- Responsibility of the subcontractor for their actions
Before use, all contracts should be reviewed by an
attorney knowledgeable in local codes and laws before
being used.
Case History: A general contractor
subcontracted a labor services company to provide jack
hammering services at a gasoline service station. The
laborer demolishing a concrete slab at a pump island
pierced a pressurized fiberglass supply line to the
pumps that resulted in the release of 1,500 gallons
of gasoline. The cleanup required the excavation and
disposal of almost 1,000 cubic yards of petroleum-contaminated
soil at a cost of approximately $80,000. Due to the
low cost of the subcontracted services, the general
contractor used a purchase order instead of the normal
subcontract agreement. The purchase order did not contain
language outlining the responsibilities of each party,
such as directing the activities of the laborer. The
general contractor was held liable for the cleanup costs.
Alternative Action: The use of a standard
contract for all subcontracted services ensures uniformity
and thoroughness when hiring subcontractors. There are
standard forms, which are readily accepted throughout
the construction industry.
There are also purchase orders available that contain
terms and conditions on the reverse side. These terms
and conditions can be modified to meet the language
and requirements of the general contract by adding an
addendum that includes the general contract by reference.
The insurance requirements for the subcontractor should
be at least equal to those your firm is obligated to
provide the owner. A copy of the general contract should
be available for the subcontractor to review. Legal
counsel should review any modifications to any type
of contractual agreement. Under no circumstances should
the general contractor sign the subcontractor's agreement
as it is most likely written in the subcontractor's
best interests.
For some subcontractors, pollution insurance should
be required in addition to the standard coverages. Commonly
subcontracted activities that should be required to
provide pollution insurance may include excavation,
demolition, HVAC, plumbing, remediation, transportation,
and any firm handling bulk liquids.
10) Obtain A Waiver of Disposal
Recommendation: When disposing of
project-generated wastes that contain potentially hazardous
materials such as lead paint, old tires, and creosote-coated
railroad ties, a waiver should be generated by the entity
disposing of the material and signed by the entity accepting
the material. The waiver must state that the entity
accepting the material is aware of the potential hazard
and the generator bears no liability for future use
or handling of the material.
Case History: A heavy highway contractor
was dismantling and reconstructing several steel beam
bridges. The contract stated that the steel was coated
with lead-based paint and disposal of the beams was
the contractor’s responsibility. This was confirmed
in the field. The contractor contacted a local scrap
steel recycling firm that accepted the material. A laborer
at the recycling facility was assigned to cut the beams
with a torch. The laborer was later diagnosed with severe
lead poisoning. A claim against the contractor for personal
injury and permanent disability payments to the laborer
was successful.
Alternative Action: This claim may
have been avoided if the heavy highway contractor had
obtained a signed waiver from the steel recycler indicating
they understood and accepted the risks of handling materials
coated with lead paint. The avoidance of liability for
future use beyond the control of the party disposing
of the waste material is documented with the use of
this waiver. The completed waiver is made part of the
project file and archived with the rest of the information.
XL Environmental • Risk Control Division •
520 Eagleview Boulevard, PO Box 636, Exton, PA 19341
• Phone: 800-327-1414 • Fax: 610-458-7285
• xlenvironmental.com
XL Environmental is a division of XL Specialty Insurance
Company.
|