Mold Prevention And Control
For Mechanical And HVAC Contractors
Mechanical contractors have an inherent risk of claims
arising out of the heating, ventilation, and air-conditioning
(HVAC) and plumbing systems installed or serviced for
their customers. An effective mold prevention and control
program can reduce such risks by proactively addressing
moisture control and quality assurance issues during
the design, construction, and commissioning phases of
the project as well as investigating and correcting
water intrusion and/or mold issues immediately. The
following are considerations for a mechanical contractor
to include in a mold prevention and control plan.
Design And Preconstruction Phase
One of the primary issues for HVAC contractors is
to ensure that the HVAC system is designed properly
for the building. If the HVAC system is “oversized,”
the system will not run long enough to dehumidify the
building. However, if the system is “undersized,”
the system may run for long periods and still not be
able to handle the moisture load resulting in condensation
on interior surfaces. Fresh air intakes need to be carefully
designed with multiple goals of diluting microbial contaminants,
energy efficiency, and moisture and temperature modulation.
There are several impacts on occupant comfort and health,
equipment maintenance, and system economics associated
with an oversized HVAC system (see Table 1). However,
equipment is routinely installed with total capacities
that are 50% to 200% greater than needed. According
to G. Hourahan in an article entitled, “Sizing
and Selecting Equipment for Proper Humidity Control,”
steps for sizing equipment correctly include the following:
- Establish building design and criteria requirements
(e.g., duct location and level of sealing and insulation,
ventilation or filtration needs, special occupant
comfort/health needs, appearance issues, building
constraints, high humidity environments, etc.).
- Determine the design loads (building construction
issues such as the building envelope, solar orientation,
glass type and shading, insulation type/level, duct
tightness/location, etc.).
- Verify system capacities (i.e., adhere to all manufacturer’s
sizing, selection, and application guidelines). Do
not arbitrarily increase the load (i.e., do not apply
a safety factor).
- Evaluate latent requirements (i.e., consider innovative
approaches to controlling moisture).
Additional design issues for mechanical contractors
to consider in a mold prevention and control program
include the following:
- Flashings at penetrations for piping and electrical
conduits, and any other HVAC equipment.
- HVAC equipment and complete flashings.
- Insulation of chilled water pipes.
- Use of mold-resistant materials (such as fire proofing,
caulks, sealants, etc.).
- Bathroom fans vented to the exterior and actuated
by the bathroom light.
- Floor drain elevations.
- Use of bare, galvanized ductwork where possible
and avoid interior linings such as fiberglass since
such linings can serve as a habitat for mold growth.
- HVAC designed with filters that have American Society
of Heating, Refrigerating and Air-Conditioning Engineers
(ASHRAE) Dust Spot Efficiency Rating of at least 50
percent.
- Ensure that designs are performed by qualified
and experience personnel who have been trained in
mold and water intrusion issues.
- Consider incorporating an automated building monitoring
system (to measure relative humidity, temperature,
and carbon dioxide) into the design to proactively
monitor the performance of the building’s ventilation
system.
- Peer review of mechanical system designs (including
shop drawings and detail drawings). Consider the use
of a third-party design review.
- Document any recommended changes given to the Architect/Engineer
of Record. Obtain approval from the architect/engineer
prior to proceeding. If the recommendation is rejected,
restate the recommendation in writing with a copy
to the owner, general contractor, and project file.
- Pre-qualify potential subcontractors and evaluate
their experience and technical qualifications.
- Inform general contractor/construction manager
and subcontractors of mold prevention and control
program.
Early start-up of mechanical systems: Procedures and
policies for the early start-up of mechanical systems
should be established. Depending on the geographical
location of the project and the type of project, an
early startup of the mechanical system may be done to
provide heating or cooling and/or drying out the building
of excess humidity. However, if the system is to be
turned on while there is still construction dust being
created, precautions should be taken so the interior
ductwork does not become coated with construction dust,
which is especially problematic if the ductwork is lined
with fiberglass. The construction dust provides a food
source for potential mold growth.
Construction Phase
During the construction phase, an inspection procedure
should be instituted and documented throughout construction
of the project with a plan to identify mold and potential
water intrusion. Photos of all key installations should
be taken. Independent inspections of major phases of
the construction work should be considered as such third-party
inspectors may become pre-deposed experts for the defense
of a mold or water intrusion claim. The inspection procedure
should include the following:
- Inspect materials to be used and delivered to the
site. Confirm that they are free of mold and water
damage.
- Confirm that all plumbing, electrical, and duct
penetrations are properly sealed to ensure water cannot
enter the structure.
- Assure materials are properly stored and protected
from moisture.
- Seal door and window openings, pipe chases, elevator
shafts, roof openings and penetrations from weather.
- Insulate all chilled water pipes.
- Remove standing water from the building(s).
- Protect ongoing and completed flashings, waterproofing,
roofing and vapor barriers during construction.
- Repair damaged materials promptly.
- Keep drains open and unobstructed.
- Repair plumbing leaks immediately.
- Remove trash and debris from the building on a
regular basis.
- Remove wet and/or moldy materials from the site
immediately.
- Install sump pumps and place them in operation
as early as possible to prevent flooding. Consider
battery-operated sump pumps.
- Place equipment that requires water (such as tile
saws, mixers, etc.) in tubs during indoor operation
to control the spread and seepage of water.
- Test plumbing and HVAC systems in accordance with
local and national codes to ensure there are no leaks
and keep signed test records with project documentation.
- Use various methods of testing of piping (such
as air tests) prior to water tests.
- Charge domestic water lines to the building structure
for as long as possible prior to the installation
of drywall to help identify potential hidden leaks.
- Confirm proper backfilling of trenches within the
buildings to prevent water from entering.
- Inspect shower receptor installations for proper
sealant.
- Check bathtubs for leaks with special attention
to overflows.
- Confirm proper installation of protection plates
on framing members per code to protect plumbing lines.
- Seal ductwork at separations if demolishing existing
systems and remove from building.
- Confirm that procedures are followed to ensure
that construction dust being created does not cause
the interior ductwork to be coated with dust in the
event of early start-up of HVAC systems.
- Confirm the receipt and execution of all change
orders and schedule changes are documented and maintained
in the project files.
Prior to turning over mechanical systems to the client,
the following are prudent steps to consider:
- Conduct a documented walkthrough inspection with
the general contractor or owner (as appropriate) to
identify and correct nonconformances. The walkthrough
inspection should cover all critical areas.
- Measure the humidity levels of the building.
- Check condensate pans to ensure they are clean.
The condensate drain should be checked to ensure it
is working properly.
- Maintain the documentation of the walkthrough inspection
in the project files.
Upon final acceptance of the mechanical systems, an
operations and maintenance manual should be provided
to the client that includes both general and equipment-specific
manufacturers’ operations and maintenance procedures
and mold prevention tips for owners (such as responding
to water intrusions immediately, fixing water or sewer
leaks immediately, using air-conditioning in hot/humid
weather, keeping HVAC system drip pans clean and unobstructed,
maintaining humidity levels between 30% and 50%, communicating
mold prevention tips to building occupants, etc.). The
owner should be informed that extended shutdowns of
the HVAC unit such as during nights and weekends or
other periods where the building is unoccupied may appear
to be cost-effective but in reality may create fluctuations
in the moisture content throughout the building and
create an environment conducive to mold growth.
Education And Training
Education and training are important elements in a
contractor’s mold control and response program.
Essentially, personnel should be trained in accordance
with the contractor’s specific procedures for
controlling mold and water intrusion issues and how
to respond to such issues. Additionally, personnel should
receive mold awareness training that includes the causes
of indoor mold growth, toxicological impact on human
health (real or perceived), and risks associated with
mold growth to third parties. Customers should also
be provided with information and guidance on maintenance
procedures and mold prevention tips as previously discussed.
Response Procedures
Upon notification of water intrusion and/or mold growth,
the site should be inspected immediately since mold
may grow on water damaged materials within 24 –
48 hours. Notification should subsequently be provided
to the insurance carrier and other parties affected
by the water intrusion. The following basic parameters
should be determined during the preliminary investigation:
- How long has the water intrusion occurred?
- What is the source of the water/moisture intrusion?
Is the source from sewage?
- Has visible mold growth occurred?
- What is the size of the water damage or mold growth?
- How can the source of water intrusion be corrected?
A qualified professional, experienced in indoor air
quality and mold assessments, should be consulted if
necessary. The following is a checklist for investigating
and evaluating moisture and mold problems:
- Assess the size of the water damage or mold area
(in square feet).
- onsider the possibility of hidden mold.
- Clean up small mold problems and fix the source
of moisture before they become large problems.
- Select a remediation manager for medium or large
mold remediation projects.
- Investigate areas associated with occupant complaints.
- Identify and correct the source(s) of water/moisture
intrusion.
- Note the type of water-damaged materials.
- Check inside the air ducts and air-handling unit.
The source of water/moisture intrusion and damaged
porous materials should be removed and replaced as soon
as possible to minimize the extent of the damage. The
New York City Department of Health (NYCDH) and the United
States Environmental Protection Agency (USEPA) have
established remediation guidelines for performing mold
remediation in schools and commercial buildings. Remediation
should be performed by qualified and trained personnel.
Table 1 – HVAC Oversizing Impacts
Comfort
- Large temperature differences between rooms
- Degraded humidity control
- Drafts and noise
- Occupant discomfort/dissatisfaction Equipment
- Larger ducts installed
- Increased electrical circuit sizing
- Excessive part-load operation (i.e., frequent cycling,
shorter equipment life)
- Nuisance service calls
Economic
- Higher installed costs
- Increased operating expense
- Increased installed load on the public utility
system
Health
- Potential to contribute to mold growth
- Potential to contribute to asthma and other respiratory
conditions
(Reference: Hourahan, G. “Sizing & Selecting
Equipment for Proper Humidity Control.” ARI Magazine.
Spring 2003: 24-34)
REFERENCES
- Arthur J. Gallagher Construction Services. “Mold
Action Plan: A Map to Avoiding Mold Litigation.”
- Hourahan, G. “Sizing & Selecting Equipment
for Proper Humidity Control.” ARI Magazine.
Spring 2003: 24-34.
- Mahoney, D. and Spear, J. “Mold Risk Assessment
& Remediation.” Professional Safety. Aug.
2003: 20-31.
- Sheet Metal and Air Conditioning Contractors’
National Association, Inc. Duct Cleanliness for New
Construction Guidelines. Virginia: SMACNA, 2000.
XL Environmental • Risk Control Division •
520 Eagleview Boulevard, PO Box 636, Exton, PA 19341
• Phone: 800-327-1414 • Fax: 610-458-7285
• xlenvironmental.com
XL Environmental is a division of XL Specialty Insurance
Company.
|