|
Design/Build: Close Coordination
Among Team Members Is Critical To Project Success
By Bennett D. Greenberg and Rachel A. Sens
Seyfarth, Shaw, Fairweather & Geraldson
Washington, DC…Construction and design firms
joining forces to perform a design-build contract must
take great care when structuring their relationship
and allocating responsibility for satisfying the owner’s
requirements.
The failure of one party to perform its function properly
can expose the other member of the venture to significant
losses. It is for this reason that parties joining forces
must carefully choose who they work with, coordinate
their work efforts and maintain close communications,
and structure a contractual arrangement which will protect
themselves from any loss they may incur as a result
of the other party’s failure to perform faithfully
their contractual obligations.
The case of CRS Sirrine, Inc. v. Dravo Corp., et al.,
445 S.E. 2nd 782 (Ga App. 1994), aff’d, 464 S.E.
2nd 897 (Ga App. 1995), is an unfortunate example of
the problems that can develop between members of a design-build
joint venture when one party fails to perform in the
manner anticipated by the other. In CRS Sirrine, Weyher/Livsey
(a subsidiary of Dravo) and CRS Sirrine ("Sirrine")
agreed to pursue a fixed price design-build contract
for the construction of a power plant for the Navy.
Weyher/Livsey had significant experiences constructing
large power projects, while Sirrine had experience designing
and engineering projects of this kind.
The parties entered into a letter agreement whereby
Sirrine would assume the lead in preparing a technical
proposal which was to be evaluated by the Navy. If the
technical proposal was accepted by the Navy, Weyher/Livsey
would assume the primary responsibility of preparing
the bid to the Navy. The letter agreement further provided
that although Sirrine was responsible for supplying
the technical information needed to prepare the bid,
Sirrine would not guarantee the accuracy of Weyher/Livsey’s
estimates used in preparing the bid. Weyher/Livsey’s
and Sirrine’s technical proposal was accepted,
and a bid for $100 million dollars was submitted and
ultimately accepted by the Navy. The parties then executed
a Joint Venture Agreement setting forth their respective
responsibilities.
Under the Joint Venture Agreement, Sirrine was responsible
for taking steps to design the project within budget,
tracking its design quantities and notifying Weyher/Livsey
if budget quantities would be exceeded. Weyher/Livsey
was responsible for the actual construction of the project.
The Joint Venture Agreement also contained a number
of other significant provisions that attempted to allocate
responsibility for cost overruns. In Article 9, each
party accepted full responsibility for its scope of
work and would indemnify the other for damages resulting
from untimely, defective and nonconforming work. Article
9.3 provided that notwithstanding any other provision,
Sirrine shall have no risk or liability for construction
material quantity overruns if the actual quantities
are different from those bid to the Navy. This provision
further provided that Weyher/Livsey would provide Sirrine
with budget quantities for all functional areas of the
project and Sirrine’s detailed design would make
every reasonable effort to stay within those quantities
within the requirements of the prime contract. Article
9.3 also provided that Weyher/Livsey would be notified
promptly if Sirrine believed quantities would be exceeded.
Article 9.2 of the Agreement stated that notwithstanding
Article 8.2 (the indemnity provision), Sirrine would
only be liable to Weyher/Livsey for costs Weyher/Livsey
incurred in excess of $750,000.00 as a result of Sirrine’s
engineering errors. This limitation was conditioned
on Sirrine providing Weyher/Livsey notice of its errors.
Lastly, the Joint Venture Agreement made clear that
it was the entire agreement between the parties, and
that all prior written agreements were terminated and
merged into the Joint Venture Agreement.
Weyher/Livsey incurred construction losses in excess
of $30 million dollars and subsequently brought suit
against Sirrine alleging that Sirrine’s breaches
caused over $12.5 million dollars of Weyher/Livsey’s
added construction costs. Specifically, Weyher/Livsey
argued that a substantial portion of its damages resulted
from the fact that quantities of materials needed for
constructing the project greatly exceeded the estimates
for construction material provided by Sirrine on which
the joint venture’s fixed price bid was based.
Sirrine, in turn, argued that Section 9.3 of the Joint
Venture Agreement unambiguously released Sirrine from
any responsibility for damages resulting from increases
in construction material quantities.
The trial court disagreed with Sirrine’s arguments
and found that Sirrine breached its contractual and
fiduciary duties (1) to provide sufficient, accurate
information to Weyher/Livsey upon which to base its
bid, (2) to make reasonable efforts to design the project,
(3) to track quantities in its design, and (4) to notify
Weyher/Livsey that quantities would be exceeded. The
trial court then apportioned fault between Weyher/Livsey
and Sirrine and concluded that Sirrine’s breaches
caused damages to Weyher/Livsey in the amount of $5,518,821.00.
Both parties appealed.
On appeal, the Appeals Court determined that the trial
court’s interpretation of the contract as ambiguous
was correct and that it did not shield Sirrine from
responsibility for increases in construction material
quantities. Specifically, the Court agreed with the
trial court’s interpretation that the intent of
Section 9.3 of the Joint Venture Agreement was that
Weyher/Livsey, and not Sirrine, should bear responsibility
for damages caused by Weyher/Livsey’s own errors
in estimating and in bid preparation, but that Sirrine
should remain responsible for damages resulting from
its pre-bid design and engineering errors. As far as
the post-bid construction phase of the project, the
Court noted that Section 9.3 imposed an affirmative
obligation upon Sirrine to make every reasonable effort
with its detailed design to stay within budgeted quantities
and to notify Weyher/Livsey if Sirrine believed the
quantities would be exceeded.
The Court also noted that evidence was introduced at
the trial court where a Sirrine official admitted that
it was not Sirrine’s intention to shield itself
from liability regardless of the quality of Sirrine’s
work. Furthermore, the Court agreed with the trial court
that Article 9.2 constituted in effect a $750,000.00
deductible for damages resulting from engineering errors
and omissions detected by Sirrine and noticed to Weyher/Livsey
with the required notice of errors and omissions under
this section.
The Appeals Court, however, remanded the case back
to the trial court because it could not reconcile the
trial court’s apportionment of damages with the
amount of the verdict. On remand, the trial court again
found that Weyher/Livsey was entitled to $5,518,812.
This decision was later affirmed by the Court of Appeal.
The CRS Sirrine case clearly demonstrates that the
success of a design/build project is dependent on design
and construction firms understanding and fulfilling
their respective obligations. This will obviously require
that design and construction firms cooperate with each
other and coordinate their activities to ensure that
each party fulfills its obligations so as to permit
the design/build team to satisfy its obligations under
its contract with the Owner.
It is also clear from this case that parties should
take great care in selecting the firms they are going
to team with, and structuring their contractual agreements
to shield and protect each party from the other party’s
inability or failure to perform by its contractual obligations.
First appeared in Design-Build Institute of America
DATELINE newsletter.
|